Very Thin High Performance Precast Concrete Elements as Permanent Schuttering and Part of Final Composite Structures - Concretan

Very Thin High Performance Precast Concrete Elements as Permanent Schuttering and Part of Final Composite Structures

Very Thin High Performance Precast Concrete Elements as Permanent Schuttering and Part of Final Composite Structures

Very Thin High Performance Precast Concrete Elements as Permanent Schuttering and Part of Final Composite Structures 1431 954 Concretan

Konstantinos  Zavliaris  M Sc. Ph.D  C.E
1st CONCRETE INNOVATION CONFERENCE: OSLO Norway 11 – 13 June 2014.

Utilization of very thin (20-50 mm )  Precast Concrete Elements of High Performance Concrete  used as permanent Shuttering for the cast in place Load  bearing  Members  can be a very efficient construction method in terms of structural Integrity of the final structure, quality, short construction time and low cost. These benefits can be further developed  by connecting the Precast concrete Elements to the corresponding  cast in place in common Action as final composite Elements.

Areas of application include Concrete Structures where extensive propping of the conventional Formwork is required, structural Members with complicated Shape or high degree of repeatability or where the completion Time is short.

The method was applied in the new Queen Allia international Airport in Amman, Jordan. /Pict 1.

The 100.000 m2 Roof of the three new Terminals was  designed by the Architect (Foster and Partners) consisting of three main Modules : a) column Head on top of the cast in place columns, an X-shaped vertically curved beam and modified spherical shells of 36.00 m diameter. The system developed by the author provided  for thin Precast High Performance Concrete Column Heads ( 7.00 m in diameter and 3.00 m high) and  two halves of X-Beams (25.00 m long )/Pict 2,   functioning as fair face permanent shuttering and Segments of  Shells (with the smallest being 11.00*12.00m) 50 mm thick in the Apex/ Pict 3  functioning as fair face permanent Shuttering and as bottom Part of the final composite

All the Elements  were precast in steel Molds in the Site  Precast Factory in an area of 15.000 m2 made available by the Owner for the duration of construction, transported by trailers to a distance of 2 km and erected at Levels 22.00 to 27.00 m from the Ground. The steel fiber reinforced concrete mix had a characteristic 28 day strength of  80 MPa and designed utilizing locally availbale aggregates with maximum size 12 mmm.  The challenges held by the application were the small thickness of the precast Elements combined with the complex geometry of the Modules and the requirement for fare  face concrete  which remained  unpainted and the composite action of the final Shells./Pict 4.

The Molds were brought to the site factory in August 2009   and the whole roof was completed in  July 2011 with a gap time of 4 months.

 

Pict 1

Pict 2

Pict 3

Pict 4